Dynamic and motivated professional with extensive experience in construction and energy industry inclusive coal fired & combined cycle power plant with total experience of 9 years. Having a proven experienced in power plant operation including shutdown & commissioning, Work Permit Management inclusive of permit issuance, system isolation & normalization, expertise in Plant Process for CCPP & CFPP, plant shutdown, commissioning & startup activities, familiar with DCS, defect/ punch list coordination with discipline engineer, plant performance analysis and root cause analysis, preparing or updating Technical Working Instruction and working procedure.
Plant Performance Monitoring
• Gas Turbine Frame 9HA.02 – Fuel Gas System, Lube Oil System, Air Intake, Diverter Damper, EV & SEV Combustor, OTC (Once Through Cooling), DCM (Dump Condenser Module), GT Shaft Monitoring Vibration & Temperature, GT Force Cooling, Compressor Cleaning, Fuel Gas Preheater, GT Protection.
• Steam Turbine with its auxiliary system – Lube Oil System, Gland Steam Sealing System, Hydraulic System, Drain System, ST Shaft Vibration & Temperature Monitoring.
• HRSG (Heat Recovery Steam Generator) – High Pressure (HP), Intermediate Pressure (IP), Low Pressure (LP), Blowdown system, Soot blower system (for Coal Fired Plant), Main & Bypass Stack, Continuous Emission Monitoring System (CEMS) for NOx, CO, So2, O2
• Water Steam Cycle – HP Bypass, IP/LP Bypass, Feedwater System, Condensate System
• BOP (Balance of Plant) – Main Cooling Water (MCW), Closed Cooling Circuit Water (CCCW),Plant Air Compressor, Condenser Tube Cleaning, Fuel Gas Heater, Electro Chlorination Plant (ECP), Water Treatment Plant inclusive of Multi Media Filter (MMF), Reverse Osmosis (RO), Mixed Bed Exchanger, Chemical Dosing, Sampling System, Waste Water Treatment Plant (WWTP),Firefighting System.
VI Certified Vibration Analyst - CAT II
Sky Residence Condominium Project
Title: Development of 5 Blocks Condominium 26-33 Storeys (1039 units) on lot 5590 and 5591, Puchong Jaya, Petaling.
The goal of this project is to complete the construction of the condominium with Certificate of Completion (COC) within the given contract period.
Turnaround Projects
Title: Plant heat rate optimization by reducing Carbon Oxide emission at full load.
The project focuses on reducing heat loss due to Carbon Oxide (CO) emission by operating the boiler at excess Oxygen at 3.2% at full load.
Title: Plant heat rate optimization by improving condenser vacuum pressure.
The project aims on improving the condenser vacuum by carrying out condenser cleaning during outage. The project creates a recurring cash impact of RM1,345K per annum.
Title: Installation of New Condensate Recovery Line from Soot-Blowing Drains to Continuous Blowdown Tank.
The project targets on improving the plant heat rate variance by 5.33KJ/Kwh (17.4%) by minimizing the steam loss from warming up the soot blowing drain line. The project creates a savings of RM231K per month.
• Speaker @ Korean Society of Mechanical Engineers (KSME) Annual Meeting 2023 International Session.
• Speaker @ International Conference on Management and Communication 2019.
• Published journal article titled Effect of bearing wear on linear and nonlinear responses of a rigid rotor supported by journal bearing in Journal of Mechanical Science and Technology (JMST) 2024
• Published journal article titled Effect of wear on the dynamic characteristics of a rigid rotor supported by journal bearings in Journal of Scientific Reports 2024
VI Certified Vibration Analyst - CAT II
NIOSH Authorized Entrant and Standby Person for Confined Space (AESP)
EIMAS DOE Certified Environmental Professional in Scrubber Operations (CePSO)
DOSH Internal Combustion Engine (ICE) Engineer Grade II
DOSH Steam Engineer Grade II
MBOT Professional Technologist
RAM-UKM Certified Malaysian Capital Market
IEM Graduate Member